Dispute With Builder Leads to Costly Outcome for Homeowner

19th March 2020 By

If you are involved in a dispute with your builder, taking sound legal advice is by far the best means of ensuring that matters do not get out of hand. One householder who failed to take that sensible course found himself embroiled in costly legal proceedings and on the receiving end of a substantial bill.

The man engaged a building firm to deal with some persistent leaks in his basement. Rather than entering into a fixed-price contract, he orally agreed to pay the firm a daily rate for its work. After forming the view that the firm was disreputable, he dispensed with its services before the work was complete.

The firm’s bill went unpaid and, after it referred the dispute to an adjudicator, he directed the man to pay the firm £6,456 for its work, together with his £3,726 fee. The man not having paid either of those sums, the firm launched High Court enforcement proceedings against him.

Ruling on the matter, the Court noted that the Housing Grants, Construction and Regeneration Act 1996 gives parties to a construction contract the right to refer a dispute to adjudication. Excluded from that provision, however, are contracts where the works concerned are to a residential dwelling occupied as a residence by one of the parties. On the face of it, therefore, the adjudicator had no jurisdiction to consider the dispute.

However, it is well established that, even where there is no formal jurisdiction, an adjudicator’s decision will be treated as enforceable where both sides in a dispute have engaged fully in the adjudication process on the merits. The man had done just that and there was no question of him having been put under duress to participate. He had thus waived his right to challenge the adjudicator’s decision on jurisdictional grounds and his ignorance of the law was no defence.

The Court also rejected the man’s plea that the adjudicator had given an appearance of bias. He had been appointed by an independent third party, the President of the Chartered Institute of Building, and was adamant that none of the firm’s personnel were known to him prior to the dispute being referred to him. It was also no part of the Court’s role to second-guess the adjudicator’s conclusions on the merits. The firm was granted summary judgment against the man in the full amount of the adjudicator’s award.

Source: Concious

Latest News

Company Owner's Negligible Value Claim Unsuccessful

29th April, 2024 By

When an asset falls in value to the point that it is almost worthless, it may be possible to make a negligible value claim under Section 24 of the Taxation of Chargeable Gains Act 1992. The asset will then be treated as if it had been sold and immediately acquired again, so that the loss can be set off against other income. For a claim to succeed, however, the asset must have become of negligible value during the time the claimant owned it. On 30 September 2017, a woman who...

Court Sanctions Leg Amputation for Man Lacking Mental Capacity

24th April, 2024 By

The courts are often called upon to sanction treatment for patients whose ability to make decisions for themselves is impaired. In a recent case on point, the Court of Protection had to decide whether it was in the best interests of a man with mental health issues to have his right leg amputated above the knee. The man, aged 60, was taken to hospital by his niece. He was found to have an ulcerated leg. He had a history of paranoid schizophrenia, and believed that the sores on his leg...

High Court Grants Parental Order Despite Previous Adoption

18th April, 2024 By

In law, adopted children are regarded as having been born to their adoptive parents. The Family Division of the High Court recently considered whether that fact precluded a parental order being granted under the Human Fertilisation and Embryology Act 2008 (HFEA) in respect of a child born via surrogacy. A couple who lived in the USA had entered into a surrogacy arrangement with another woman. An adoption order naming the couple as the child's parents had been made by a US court and was automatically recognised under UK law. However,...

Flat Owner Not Liable for Pre-existing Structural Issues

16th April, 2024 By

When building owners carry out works on their property, are they liable for damage to adjoining properties that results from pre-existing structural issues? The Court of Appeal recently provided welcome clarification on that question. The owner of a ground-floor flat wished to extend it by building out into his garden. He served notices on owners of adjoining properties, as required by the Party Wall etc. Act 1996. The works caused the rear wall of two adjoining properties to drop by about 2 mm, which led to internal walls and floor...