When Is a New Home Complete? DIY Housebuilders Win £14,000 VAT Rebate

4th June 2020 By

One of the benefits of building your own home is that you can claim back VAT paid on materials used in the project – but rebate applications have to be made within three months of the property’s completion. That time limit came under analysis in a case concerning a couple who took almost 20 years to achieve their grand design.

The couple had long wished to build their own home and obtained planning consent for a detached property in 1998. Work progressed slowly, however. Although they moved in in 2010, windows were not fitted to the property until 2016 and it was only in 2018 that a certificate of completion was issued by the local authority.

After receiving the certificate, the couple promptly applied for a VAT rebate of over £14,000. HM Revenue and Customs (HMRC), however, refused the application on the basis that the property had been completed in either 2010 or 2016 and that the three-month deadline, set by Regulation 201 of the Value Added Tax Regulations 1995, had therefore long since passed.

Challenging that decision before the First-tier Tribunal (FTT), the couple said that they had relied on advice that they received at a VAT seminar organised by HMRC. They were unaware of Regulation 201 or that the date on which they took up occupation of the property might be viewed as important. They had understood that they had unlimited time in which to finish the project and had swiftly submitted their rebate claim when they considered that the house was complete.

In upholding their appeal and their entitlement to the rebate, the FTT assumed that Regulation 201 was framed in a way which was intended to make it relatively straightforward for taxpayers, and HMRC, to determine when completion of a building has taken place. Uncertainty as to the date of completion was likely to foster dispute and leave taxpayers in an impossible position.

In order for a building to be complete, the FTT found that it must be finished in line with the plans for which planning consent was granted and be capable of fulfilling its purpose as a safe, hygienic and habitable home. In the couple’s case, completion was only achieved when the property was finished to a standard equivalent to that which a commercial housebuilder would be required to meet. On that basis, their home was not completed before the certificate of completion was issued and their rebate application was therefore in time.

Source: Concious

Latest News

Tenants Can Purchase Freehold When Landlord Cannot Be Found

11th June, 2024 By

The Leasehold Reform, Housing and Urban Development Act 1993 gives qualifying leaseholders the right to join together to buy the freehold of their properties – a process known as collective enfranchisement. A recent case demonstrated that this right can be exercised even when the landlord cannot be found. The leaseholders of two flats in a terraced house wished to purchase it from the landlord, but were unable to ascertain his whereabouts and therefore could not serve notice on him under Section 13 of the Act. They therefore applied for an...

Court Refuses to Set Aside Divorce Order Applied for by Mistake

6th June, 2024 By

While the courts have a range of powers to set aside orders, they will only exercise them in limited circumstances. In a somewhat surprising case that has attracted much comment, the High Court declined to set aside a final order of divorce that had been applied for by mistake. A couple separated in January 2023, after more than 21 years of marriage. In October that year, while financial remedy proceedings were still ongoing, the wife's legal representatives inadvertently applied for a final order of divorce in respect of her instead...

Waiting Time for Grants of Probate Falls

3rd June, 2024 By

Following concerns last year about delays in processing probate applications, recent figures from HM Courts and Tribunals Service show that waiting times for grants of probate are continuing to improve. The average time from submission of a probate application to probate being granted fell to 11.3 weeks in March 2024, a decrease from 13.7 weeks in February and 13.8 weeks in January. This is the lowest figure since March 2023, when the average was 10.8 weeks. The longest waiting time since then was in November, at 15.8 weeks: that month,...

Late Appeal Against Tax Penalties Rejected

31st May, 2024 By

It is incumbent on taxpayers to make sure they fully comply with their obligations to file returns and pay any tax due. The point was illustrated by a recent case in which a taxpayer whose return had not been received by HM Revenue and Customs (HMRC) failed to persuade the First-tier Tribunal (FTT) that he should be permitted to appeal against the resulting penalties. On the evening of 31 January 2014, the man had completed his 2012/13 Income Tax return on HMRC's website. Shortly afterwards he went to Cyprus, and...